The crews have begun the installation of the roof trusses and expect to have the roof completed by the end of the month. Trucks loaded with fill dirt are arriving daily to bring the grading in the parking lot to the necessary two foot height.
(Photos and video taken on January 10 & 13, 2025)

Grading the parking lot and preparation for baserock.

The surveyed parking area where crews conducted cut and fill for the parking spaces.

The surveyed parking area where crews conducted cut and fill for the parking spaces.

Delivery of roof trusses.